Isiolo-Mandera Highway Delays Risk KSh1.2 Billion in Monthly Costs, World Bank Warns

Alphie Yesterday, 10:15 AM 2 min read
Isiolo-Mandera Highway road project

The World Bank has urged Kenyan officials to address compensation delays that restrict contractors’ access to land along the KSh168 billion road project.

The World Bank has warned Kenya that compensation delays on the Isiolo-Mandera Highway could add approximately KSh1.2 billion in monthly costs. Contractors cannot fully access land needed for construction along the KSh168 billion project.

World Bank Division Director Qimiao Fan raised the concerns in a letter to three Cabinet secretaries. They are Treasury’s John Mbadi, Roads and Transport’s Davis Chirchir, and Lands’ Alice Wahome.

Fan said delayed payments were disrupting construction schedules and increasing the risk of cost overruns. Some sections cannot proceed as planned because contractors lack unrestricted access to the land.

Advertisement

Isiolo-Mandera Highway compensation delays

The bank said financing for compensation had been available since 2024. However, payments only began in November 2025 and have so far covered only the Isiolo-Modogashe section.

The letter recorded compensation for 1,281 of the 1,669 project-affected people, leaving 388 awaiting payment. It also warned that continued delays would increase contractual risks and complicate implementation.

On the Isiolo-Kulamawe section, the government had paid KSh456 million in compensation. However, the bank estimated that delays could expose that section to KSh536 million in additional monthly costs.

Meanwhile, compensation on the Wajir-Tarbaj-Kotulo section had also faced delays, with completion expected by November 2026. The bank put that section’s potential extra monthly costs at KSh421 million.

The Kotulo-Kobo-Eluaki section also faced delays in compensation claims. Its estimated monthly financial exposure stood at approximately KSh243 million, adding to the pressure across the affected stretches.

Restricted access raises construction costs

Across six active road contracts, the bank estimated recurring monthly costs at approximately KSh1 billion. These include supervision, security, site facilities, idle machinery and personnel, price increases and other time-related expenses.

In addition, moving equipment off construction sites and returning it could cost approximately KSh207.5 million, including related overheads. Together, these estimates account for the roughly KSh1.2 billion exposure for each additional month of restricted access.

The warning therefore links compensation delays directly to the project’s construction timetable and financial risks. Fan said the bank had already released compensation funding, but payments remained delayed.

The 740-kilometre highway forms part of the Horn of Africa Gateway Development Project. Its original completion target was January 2028, but the timetable later shifted to around 2030.